Welcome

TECHNEST / Blog

The partner API is not ready: how far can offshore development go?

Separate what the Japan–Vietnam team can verify with an API mock from what requires the actual partner system, so progress reflects readiness.

A Japanese SIer needs to connect an order system to a warehouse platform, but the warehouse test environment is not yet available. The Vietnam development team can start if both sides agree on what can be built against the specification and what requires an actual connection. Put that distinction in the plan and estimate from the start.

Agree on examples both sides can use

For each priority workflow, record the specification version, sample requests and responses, the meaning of each status and how your application should behave. Include success, rejection and no-response cases. Give every unconfirmed assumption a Japan-side contact and a response deadline. The Vietnam team uses the agreed examples to build an API mock and lists the cases it does not cover.

Set two separate verification milestones

First, the Vietnam team checks that its application sends the right information and displays or handles simulated responses as required. Later, both sides rerun key scenarios in the partner’s test environment and record the business outcome in the target system. Pact’s documentation distinguishes contract tests, which focus on messages exchanged, from functional tests that check the resulting effects. [1] Label mock results as simulated in progress reports.

Hypothetical example: reserving stock for an order

Imagine a SIer wants to reserve inventory after an order is placed. The Vietnam team mocks three responses: request received, stock reserved and insufficient stock. The application marks the order as reserved only after confirmation. A receipt acknowledgement leaves it pending. This is an illustration, not a TECHNEST project result.

When the real environment opens, both sides submit a test order and ask the warehouse contact to confirm how much stock was actually reserved. If it differs from the assumption, record the difference, agree whether to change the specification or code, and rerun the relevant test. A progress update could say: “Application verified with the mock; warehouse reservation outcome awaiting confirmation.”

Budget for real integration

Record who supplies access and test data, who runs the joint tests, who confirms results and which milestone changes if the environment opens late. Estimate mock development, updates to reflect specification changes and partner-system testing separately. This shows the PM which work can continue and what may still affect delivery.

Discuss your integration with TECHNEST

TECHNEST has years of experience designing and developing business systems for the Japanese market. If a partner API is not ready, share one workflow and when you expect to be able to test it. We can help identify work that can start, checks that must wait and how to schedule both milestones.

Explore software outsourcing services · Talk to TECHNEST

Reference

[1] Pact Docs, Contract Tests vs Functional Tests.